Aerial photograph of the white five-story 11010 smB building seen from above, with a rooftop deck of planters, tables and umbrellas, a curved corner with artificial turf, a glass office building to the right and a street with a red car at the bottom
11010 smB from above, showing the rooftop deck, from the general contractor's project page. Photo: Swinerton (photograph on the contractor's project page; no photographer credit printed), Photograph of the finished building on the general contractor's own project page; the page prints no photographer credit. Used with credit as a project-team photograph of the building (docs/new-developments/CLAUDE.md section 7; the Hope on Hyde Park guide used a contractor's image the same way)., via Swinerton, 'Weingart 11010 Santa Monica Boulevard' project page (read October 30, 2026) (cropped to 16:9 from 1920 x 1438 and scaled to 1600 x 900 (smaller than the original); no other edits).
Quick answerAs of October 30, 2026, 11010 smB at 11010 W. Santa Monica Blvd, in West Los Angeles (ZIP code 90025, Council District 5), is a finished five-story building with 51 apartments. The records show 50 supportive studios and one manager's apartment. The City's listing says tenants are referred through the Coordinated Entry System, and that 25 apartments carry project-based vouchers and 25 carry HUD-VASH vouchers. No rents and no open application are published.
11010 smB in numbers
  • 51apartments in the permit and LAHD's report
  • 50income-restricted studios, plus 1 manager's apartment
  • 5 storiesper the permit, at 66 feet
  • April 23, 2024the City's certificate of occupancy
  • 25 and 25apartments with project-based and HUD-VASH vouchers, per the listing
  • Tier 11HACLA's payment standard tier for ZIP code 90025

What it means: the building is finished, and the City's listing says tenants are referred, not chosen from an application.

Source: LADBS permit 20010-10000-00015; LAHD report 19-126648; Access Housing LA listing, read October 30, 2026; HACLA payment standards effective September 1, 2026.

Words used in this report
  • Area median income (AMI)The middle income for the area, adjusted for household size. Apartments are set aside for households at a share of it, such as 30% or 50%. An income chart turns each level into dollar limits.
  • Housing Choice Voucher (Section 8)Rental help run by a housing authority. You find a home, and the agency checks the unit, rent and your household before it approves payment.
  • Payment standardAn amount the agency uses to work out housing assistance for a unit size and area. It does not mean that any home at that rent will be approved.
  • FMR and SAFMRHUD rent estimates for an area (Fair Market Rent) or ZIP code (Small Area Fair Market Rent). They include rent and most tenant-paid utilities. Your agency may use a different payment standard.
  • Utility allowanceThe agency's estimate of the cost of utilities you must pay. It is not a promise to pay your actual bills.
  • Certificate of occupancyThe Department of Building and Safety's sign-off that a building can be lived in.
  • LAHD and HACLALAHD is the Los Angeles Housing Department, which runs Access Housing LA. HACLA is the Housing Authority of the City of Los Angeles, which runs Section 8 vouchers inside the City.
  • PSH and CESPermanent supportive housing, filled by referral through the Coordinated Entry System.
  • PBVA project-based voucher, "a component of a public housing agency's (PHA's) Housing Choice Voucher (HCV) program," according to HACLA. The voucher belongs to the apartment, not to a household.
  • HUD-VASHIn state law, "a federal Department of Housing and Urban Development Veterans Affairs Supportive Housing voucher."
  • Prop HHHThe 2016 City bond for "supportive housing for homeless individuals and families," according to LAHD.
  • Density BonusCity Planning's State Density Bonus Program is "the City's primary mechanism for implementing the State Density Bonus Law (Government Code Section 65915)."

What Is Built at 11010 W. Santa Monica Boulevard

11010 smB is a five-story building of 51 apartments, built from factory-made modules. The City gave its certificate of occupancy on April 23, 2024.

  • Names: Weingart Center writes "11010 smB." Swinerton writes "11010 SMB." The City's listing says "11010 Santa Monica." LAHD and the tax-credit list use the street address. All mean the same lot.
  • Size, per the permit: permit 20010-10000-00015 reads "NEW 5 STORY 51 UNIT APARTMENT BUILDING WITH 4 STORIES OF TYPE V-A ON ONE-STORY OF TYPE I-A . 100% AFFORDABLE. SB 35 SB 1818 - AB 1763." It lists 38,245 square feet and a height of 66 feet.
  • Density, per LAHD: the project received a density bonus of "80% increase in density," for 51 units instead of the 28 the C2-1VL-0 Zone otherwise permits.
  • Owner and developer: the tax-credit list names 11010 SMB LP as owner and Weingart Center Association as developer. The listing also names Weingart Center Association as developer. LAHD names Valued Housing II, LLC. Urbanize LA calls Valued Housing Weingart's "development partner." Swinerton's page names "Weingart Center Foundation" as owner. The records do not say how these entities relate.
  • Architect and builder: Perkins&Will designed it, and Swinerton was general contractor, per Swinerton and Connect CRE. Swinerton names Silver Creek as the modular manufacturer.
  • Manager: Barker Management Inc., per LAHD, the tax-credit list and the listing.
Rendering of a five-story building with pale blue-gray walls, curved corners, a green roof edge, a ground floor with the sign 11010 smB and lit windows, trees, a street with two cars and people on the sidewalk
Rendering of 11010 smB from Weingart Center's 2021 groundbreaking release. The architect of record is Perkins&Will; the page does not name who made the image. Photo: Weingart Center Association (rendering published on its press-release page; maker not named), Rendering published by the building's owner on its own press-release page; used with credit under docs/new-developments/CLAUDE.md section 7 (images made for a building's developer, wherever published)., via Weingart Center, 'PR: New Permanent Supportive Housing for Seniors, Veterans' (July 6, 2021; read October 30, 2026) (cropped to 16:9 from 1650 x 1275 (the file has white side margins, which were cut) and scaled to 1600 x 900 (about 1.26 times enlargement); no other edits).

Swinerton says it set all 51 modules by crane in 10 days. The concrete ground floor was built at the same time.

11010 smB, from approval to the listing
  • May 19, 2020City Planning approves case CPC-2020-380-DB-SIP, per the state's progress-report data. It counts 50 low-income apartments and one other, for 55 years.
  • June 3, 2021the building permit application is submitted.
  • June 18, 2021LAHD's list shows its funding date, with $7,000,000 in City funding.
  • July 6, 2021Weingart Center holds the groundbreaking.
  • July 12, 2021the City issues the building permit.
  • 2021Swinerton's groundbreaking post projects the first residents in October 2022.
  • August 22, 2022Urbanize LA reports the modular units are in place.
  • February 10, 2023the tax-credit list shows the placed-in-service date.
  • Week of February 13, 2023officials mark the opening, per Urbanize LA's report of February 21.
  • April 23, 2024the City issues the certificate of occupancy.
  • April 21, 2025the Access Housing LA listing is published.

What it means: the permit's certificate of occupancy is 14 months after the tax-credit placed-in-service date, by VoucherMatch's count, and the records do not explain the gap.

Source: HCD Housing Element Annual Progress Report data; LADBS permit 20010-10000-00015; LAHD list; Weingart Center; Urbanize LA; CTCAC list CA-2020-695; Access Housing LA listing.

Where the Records Differ

The records disagree on the studio count, the age rule and the heat. Each figure carries its source.

Where the records differ
  • StudiosLAHD, the listing and Weingart's 2021 release say 50 studios and one manager's apartment. Swinerton's project page says "51 studio units" and also "one two-bedroom manager unit." Weingart's 2022 post says "51 fully furnished studio unit apartments."
  • AgesSwinerton says seniors and veterans "aged 62 and older." The listing says "Seniors and Senior Veterans." Its page data has no minimum age.
  • HeatWeingart lists "heating & air conditioning." The listing's page data marks air conditioning but no heating.

What it means: VoucherMatch did not pick one figure. Ask the manager for the current facts.

Source: the records named above.

How the Project Was Paid For

LAHD's report lists $7,000,000 in City funding, a $2,250,000 tax-exempt conduit bond and $20,195,507 in other funds, and VoucherMatch has not added them together.

How this article was checked

Last checked: October 30, 2026, against the Access Housing LA listing for 11010 Santa Monica; LAHD's Affordable Housing Projects List and project report 19-126648; the City's building permits issued for permit 20010-10000-00015; the California Tax Credit Allocation Committee's list of projects (CA-2020-695); the state's Housing Element Annual Progress Report data; Weingart Center's groundbreaking release, housing page and opening post; Swinerton's project page and groundbreaking post; Urbanize LA's reports of July 7, 2021, August 22, 2022 and February 21, 2023; Connect CRE of February 22, 2023; HACLA's payment standards, utility allowances and project-based voucher page; California Government Code section 12955; LAHSA's get help page; HUD's fiscal year 2027 Small Area Fair Market Rents, as carried on VoucherMatch's [ZIP code 90025 page](/section-8/zip/90025); and Metro's rail data. How VoucherMatch reports these guides and corrects errors: [how we report](/new-developments/how-we-report).

Sources for this article (22)
  1. listing for 11010 Santa Monica (access.housing.lacity.gov)
  2. Affordable Housing Projects List (data.lacity.org)
  3. project report 19-126648 (housingapp.lacity.org)
  4. building permits issued (data.lacity.org)
  5. list of projects (treasurer.ca.gov)
  6. Housing Element Annual Progress Report data (data.ca.gov)
  7. groundbreaking release (weingart.org)
  8. housing page (weingart.org)
  9. opening post (weingart.org)
  10. project page (swinerton.com)
  11. groundbreaking post (swinerton.com)
  12. July 7, 2021 (la.urbanize.city)
  13. August 22, 2022 (la.urbanize.city)
  14. February 21, 2023 (la.urbanize.city)
  15. Connect CRE (connectcre.com)
  16. payment standards (hacla.org)
  17. utility allowances (hacla.org)
  18. project-based voucher page (hacla.org)
  19. California Government Code section 12955 (california.public.law)
  20. get help page (lahsa.org)
  21. rail data (developer.metro.net)
  22. access point directory (lahsa.org)
Share:

Stay Updated on Housing

Get the latest on fair market rents, voucher programs, and finding housing.

No spam, ever. Unsubscribe anytime.

VoucherMatch Editorial Team

Every rule, date and dollar amount in this article is checked against the agency document it comes from, and the sources are listed above. How VoucherMatch articles are researched and corrected

More new affordable buildings

See all new developments in LA →Other cities →

Find Your Next Home

Explore voucher housing options and local rental guidance.